Looking for a progress report on campus construction? Here's the latest news:

The parking lot behind the Fine Arts Building is progressing on schedule and should be finished late this spring. Construction crews are currently working on the storm water retention system as well as re-routing utilities. The cost of the project is just over $1.2 million.

University Hall is running around 10 percent ahead of schedule and should be finished by late spring or early summer. The interior finishes are currently being installed in the building, and crews are finishing the site work as well as work to the front entrance of campus.

Work is almost set to begin on a total renovation of Bellevue Hall, which housed the Counseling and Testing Center. Construction will begin in January and should be completed by the end of the year.

For more construction photos see ASU Report December Photo Review.

Other News: Cullum | Graduation | Construction Update | Travel Safety | Identity Theft | News Briefs | Campus Notables | Photos 1 2 3 4 | Spotlight | Office Visit | Calendar | Birthdays | Quiz | ASU Report HOME


Augusta State University
2500 Walton Way • Augusta, GA 30904 • 706-737-1444
Produced by the Office of Public Relations and Publications