|
ASU campus undergoes unprecedented construction
Over the next few months, the campus will undergo unprecedented
construction activity. Traffic areas, walkways, and parking lots will be temporarily
affected, and a considerable amount of noise and other disruption will take place
as construction, renovation, and demolition take place. At the end of the activity,
however, will be a beautiful campus with state of the art facilities, says Kathy
Hamrick, special coordinator for master planning.
Unfortunately, progress comes with a price tag, and for us it will be in
the way of noise, vibrations, and parking and traffic problems. If we can keep
in mind what the campus will be like when all of this activity is over, then
maybe it will be easier to endure, she says. Meanwhile, we want the
campus to be prepared for a high level of inconvenience, she adds.
Projects are gearing up, with some in the planning, some in design, and others
in activity. The roadbed in front of Butler and Hardy Halls is being removed,
which will allow the area to become green space. Utilities and data/telecommunications
are being rerouted around the Butler Hall/Science Building area in preparation
for the demolition of the six old academic buildings.
A$1.4 million storm water project is continuing, which involves construction
of a loop interior road around campus. Construction, now taking place
in the lot adjoining Fines Arts Center, will continue to the south side of campus
(in front of the warehouses) and will intersect with Katherine Street in front
of the costume shop (next to Boykin Wright). This will involve temporary closures
of parts of the roads and parking lots. The project is designed to provide detention
of storm water and release onto an approved city storm water collection system.
Bellevue Hall, the oldest building on campus, is undergoing an extensive renovation,
which stripped the building of its roof, interior walls, and second- story flooring.
The original flooring on the first floor was saved.
At some point in history, a second floor was added to the early 1800s building,
without providing adequate support beams. As a result, over the years, the floor
began to sag. This is being remedied, in addition to restoring the building to
its former beauty, says Therese Rosier, director of Physical Plant.
The $880,000 renovation is expected to be completed in December.
Work toward the universitys first student housinga privatized projectis
proceeding. The design stage, by Ambling Companies, is nearly complete, and contractors
will be in place when the plan has been approved by the Board of Regents and
the purchase of the property has been completed.
The gated residential site will provide housing for about 500 students and will
be located near ASUs Wrightsboro Road property.
The design firm of 2KM Architects, headed by Rob Mauldin, is in the programming
stage for the design of the student center, meeting with university officials
and students to determine which activities and space should be included in the
approximately 50,000 square foot building. Among the new features will be facilities
for wellness and a ballroom for large group gatherings. The facility, to be built
adjacent to the library, will also provide a vending area for library patrons.
Construction is expected to start in the fall.
Construction on the 116,000 square foot University Hall is expected to be completed
in early May. Once contractors turn the building over to the University System,
the front entrance and adjoining parking lots will reopen. Information Technology
Services is scheduled for the first move .(mid-May/early June). Moves for other
occupants are being coordinated now, and a schedule will be available soon, says
Dr. Hamrick. The moves will begin in early July and be completed by early August,
in time for fall semester classes in the new building.
A timetable is being developed to coordinate all stages of the projects by consultant
Rick Toole, W.R. Toole Engineering. He is overseeing the demolition of the six-pack,
the nickname given to the six old academic buildings that are to be demolished.
Everyone has probably seen a demolition on television or in the movies,
so they should be somewhat familiar with what is involved; expect a large amount
of dust and a lot of noise and vibrations, says Ms. Rosier.
Before demolition begins, excavation and filling-in of an underground structure
near Markert Hall will have to be completed. (The structure was used by the Army
when this site was an Arsenal.) Asbestos abatement and environmental clean up
will follow.
This has probably been of concern to some, but I want to assure everyone
that the abatement will be carried out safely, says Ms Rosier. These
are professionals who are used to doing this kind of work; and they know what
they are doing. There will be no cause for concern, because every safety precaution
will be taken,she adds.
Safety was also the first concern in establishing new walkways to move foot traffic
from the lower parking lots to the interior of campus. While the demolition area
will be fenced, a safe walk is being provided in front of the radio station/CETC
building and swimming pool.
Construction continued ...
Other News:
Commencement | Employee
Recognition | Construction | NCATE
| Golf Facility | Nursing
| Music CD | Staff Excellence
| Baseball | Fulbright Grant
| Campus Notables | Photo 1
| 2 | 3 | 4
| Spotlight | Offices
| Calendar | Birthdays
| Quiz | ASU Report HOME

Augusta State University
2500 Walton Way Augusta, GA 30904 706-737-1444
Produced by the Office of Public Relations and Publications
|